LRT-1 Cavite Extension Phase 1 on track for Q4 2024 opening

Continued progress is on the horizon for the Light Rail Manila Corporation (LRMC), private operator of LRT-1, as it remains bullish on the completion of construction works and the start of commercial operation for the LRT-1 Cavite Extension Phase 1 Project in the last quarter of 2024.

LRT-1 Cavite Extension project continues to shape up as it registered a 94.1% progress rate as of the end of the third quarter of 2023 for the civil and system works of the 6.7-kilometer phase 1 project, composed of five (5) new stations that are in various stages of development.

This includes Redemptorist Station, which will be the next station after the existing Baclaran station (southbound), registering 86.3% completion; MIA Station, which will be the closest station to the airport, at 86.9%; Asia World Station, which will be connected to the Paranaque Integrated Terminal Exchange (PITX) for a more convenient transfer of commuters to other modes of transportation going to their destination, at 72.9%; Ninoy Aquino Station at 81.5%; and Dr. Santos Station, which will be the last station for the first phase of the project – with a bus terminal, sports facility, and interconnection to the nearby SM City Sucat, at 90.5%.

“We are optimistic that in less than a year, we are to begin the commercial operations of the LRT-1 Cavite Extension Phase 1 Project. The overall progress rate is a good signal to usher the country into an era of modern railway experience where passengers can take advantage of world-class amenities, user-friendly and PWD-friendly facilities, high standards of safety and security, and value-added services,” LRMC President and CEO Juan F. Alfonso said.

With construction activities in full swing, safety remains the top priority of LRMC for its workers and workplaces by carrying out programs to ensure stringent health, safety, and environmental practices among its employees and contractors. The LRT-1 Cavite Extension Phase 1 Project has recorded 358,338 safe man-hours for the month of September 2023, accumulating a total of 11.8 million safe man-hours without a lost time incident (LTI) for the project. This is a result of consistent site inspections, performance-based strategies, use of technology for a robust system of reporting, regular drills, and simulation exercises.

Mommy Iris

I'm a lifestyle and mommy blogger from the Philippines. Pinay Ads was created to share bits and pieces of my life and my family. I have a wide array of interests that include entertainment, movies, music, gadgets, traveling, food, baking, and more. So, I hope you’ll stick around and enjoy reading!

Recent Posts

Stay Cool and Efficient This Summer with Sharp Air Conditioner

Summer is fast approaching, and as early as now we are thinking of ways to…

8 hours ago

MOVE Into Your Ready Home in Key Growth Centers With Vista Land Ready-for-Occupancy Properties in Mega Manila and Central Luzon

Vista Land, the Philippines’ leading integrated property developer, continues to bring the lifelong dream of…

19 hours ago

Anko to open third and largest store in the Philippines

Anko, Australia’s much-loved home and lifestyle brand, is set to open its third and largest…

23 hours ago

Ice Made Cooler: LG Refrigerators Are Ready to Turn Up the Cool at BGC

Get ready for a whole day of experiences packed with exciting activities as LG brings…

2 days ago

Why Proprietary Firms Are Expanding Beyond Forex Trading?

Trading companies give money to traders. This helps traders earn profit and lessens their money…

3 days ago

PayMongo Celebrates 6 Years: Launches Financial OS and Fast Onboarding for Filipino Businesses

Manila, Philippines — Marking six years of fintech innovation, PayMongo has introduced its most significant transformation…

1 week ago